How to set a preventive maintenance with the work order opening date?
On the work orders tab, it is possible to define the
scheduling criteria that affected the date of the following event, based on the
previous work order.The
opening date criterion must consider the first transition to a state that
allows to log work or costs. If
the initial state allows records, the work order date must be considered.
Example of scenarios:
- Tolerance of zero days: - Preventive on the first Monday of every month:
Event
| Expected Date
|
1
| 09/02/2022
|
2
| 09/03/2022
|
3 | ... |
- Tolerance of 10 days - Monthly preventive every 9th day of the month
- Advance and delay tolerance of 10 days
- Example of an event inside the tolerance, with no state
transitions: The Event is opened on
02/09/2022, with state transitions (inside the 10 day tolerance), the event
date is the Work Order date.
Event | Expeted Date |
1 | 02/09/2022 |
2 | 03/09/2022 |
3 | 04/09/2022 |
- Example of an event outside the tolerance:- The Event is opened on 02/09/2022, and transitioned to a state that
allows to log work or costs on the 02/20/2022 (transition of SLA end outside
the 10 days tolerance)
Event | Expeted Date |
1 | 02/09/2022 |
2 | 03/09/2022 |
3 | 04/09/2022 |
- Tolerance of 365 days - The tolerance of 365 days is equal to 0, that is, when applying the
tolerance, it returns to the same day as the event
Related Articles
How to create a preventive maintenance?
Preventive maintenance specifies a set of maintenance actions to be performed based on a fixed recurrence or on meter values. To create a new preventive maintenance, select the option Work | Preventive Maintenances: The list of preventive ...
Calculating Preventive Maintenance events with counters and Opening or Closure scheduling criteria
The cumulative reading value of a preventive maintenance event becomes the same as the last counter reading when: the Work Order has an associated preventive event; the event is the last one with an associated Work Order (most recent); the preventive ...
How to join plans on the preventive maintenance?
When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...
How to set a preventive maintenance with fixed date?
On the Work Orders tab, you can set the scheduling criteria to set the event on a fixed date, when applying this configuration, the events will always be created on the set date. This criterion is not influenced by the previous work order dates, that ...
How to set a preventive maintenance with the work order closing/opening date?
When creating a preventive maintenance, on the "Work Orders" tab, it is possible to define the scheduling criteria that affected the date of the following event, based on the previous work order. On the "Scheduling", it is possible to select one of ...