How to set a preventive maintenance with the work order closing/opening date?

How to set a preventive maintenance with the work order closing/opening date?

When creating a preventive maintenance, on the "Work Orders" tab, it is possible to define the scheduling criteria that affected the date of the following event, based on the previous work order.  On the "Scheduling", it is possible to select one of the following options:
  1. Fixed date: This criterion is not influenced by the previous work order dates, that is, they always occur on the same date. 
  2. Opening date: This criterion is based on the previous work orders opening date, that is, the opening date is considered by the work orders' state, configured to allow to report work or costs. If the initial state allows work or cost records, the work order date must be considered.
  3. Closing date: This criterion is based on the previous work orders closing date, that is, the closing date is considered by the work orders' state, configured as SLA end.




    • Related Articles

    • How to create a preventive maintenance?

      Preventive maintenance specifies a set of maintenance actions to be performed based on a fixed recurrence or on meter values. To create a new preventive maintenance, select the option Work | Preventive Maintenances: The list of preventive ...
    • Calculating Preventive Maintenance events with counters and Opening or Closure scheduling criteria

      The cumulative reading value of a preventive maintenance event becomes the same as the last counter reading when: the Work Order has an associated preventive event; the event is the last one with an associated Work Order (most recent); the preventive ...
    • How to join plans on the preventive maintenance?

      When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...
    • How to set a preventive maintenance with fixed date?

      On the Work Orders tab, you can set the scheduling criteria to set the event on a fixed date, when applying this configuration, the events will always be created on the set date. This criterion is not influenced by the previous work order dates, that ...
    • What is preventive maintenances batch management?

      Preventive maintenances management was designed to allow you to simultaneously change the state, delete or create new versions for a set of preventive maintenances. For that, you must access Work | Preventive Maintenance | Preventive Maintenance ...