How to create a new version of the preventive maintenance?

How to create a new version of the preventive maintenance?

Creating new versions allows you to improve preventive maintenance by reusing the current configuration. To create a version, access Work | Preventive Maintenances;

  1. The list of preventive maintenances will be displayed;
  2. Select the preventive maintenance and press the View option. You can only create a new version for preventive maintenances on the “Approved” state;
  3. On the Operations link, select the option New Version. This new version is created and the record is loaded to the screen;
  4. Click Edit, make the necessary changes and press the Save button.

When creating a new version must consider the following points:

i.The new version is created in the “New” state;

ii.When the new version changes to the "Approved" state, the previous version changes to the "Replaced" state.

When clicking the New Version option, the preventive record is created immediately and is then available for editing.

If you wish to discard the changes in this version before approving, click the Delete icon and the new version will be deleted.


    • Related Articles

    • How to create a preventive maintenance?

      Preventive maintenance specifies a set of maintenance actions to be performed based on a fixed recurrence or on meter values. To create a new preventive maintenance, select the option Work | Preventive Maintenances: The list of preventive ...
    • What is preventive maintenances batch management?

      Preventive maintenances management was designed to allow you to simultaneously change the state, delete or create new versions for a set of preventive maintenances. For that, you must access Work | Preventive Maintenance | Preventive Maintenance ...
    • How to create work orders from a preventive maintenance event?

      From a preventive maintenance event, you can create a work order automatically or on user request.      i.Automatically for the Work Order to be automatically generated on the preventive maintenance file, the state in which the work order is created ...
    • How to set the preventive maintenance's time zone?

      Preventive Maintenance allows you to set the time zone in which events must occur. This way you can locally setup events that must occur on the day and at the time of the place where the work will be performed. The event preview displays events that ...
    • How to join plans on the preventive maintenance?

      When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...