How do I create a work order for a route from a preventive maintenance event?

How do I create a work order for a route from a preventive maintenance event?

It is possible to create a work order automatically or at user request from a preventive maintenance event:

  1. Automatic creation
    1. For the Work Order to be generated automatically on the preventive maintenance sheet:
      1. The state in which the work order is created must be defined in the WO Status field;
      2. The automatic reprogramming service must be activated;
    2. On the day the event takes place, when the service is performed, the associated work order will be created.
  2. Creation at user request
    1. To manually create a work order, you need to:
      1. Go to the list of preventive maintenance events, at Work | Preventive Maintenance  | Preventive Maintenance Events;
      2. Select the event and in the Operations link, select the Create Work Order option.

Alert
Once the Work Order has been generated, the assets of the selected route are associated with the work order.
Assets that are new on the route after the Work Order has been generated will not be associated.

Notes
Route assets marked as inactive will not be associated.
Route elements in downtime are associated with the Work Order.


    • Related Articles

    • How to create work orders from a preventive maintenance event?

      From a preventive maintenance event, you can create a work order automatically or on user request.      i.Automatically for the Work Order to be automatically generated on the preventive maintenance file, the state in which the work order is created ...
    • How to create a preventive maintenance?

      Preventive maintenance specifies a set of maintenance actions to be performed based on a fixed recurrence or on meter values. To create a new preventive maintenance, select the option Work | Preventive Maintenances: The list of preventive ...
    • How do I change the preventive event date on the event form?

      On the preventive maintenance event form, you can postpone or delay the event date according to the following rules: The new event date must not be earlier than the previous event or later than the next one, in order to maintain the order of the ...
    • How to join plans on the preventive maintenance?

      When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...
    • How to create a work order?

      The Work Order (WO) is the entity that represents the maintenance job to be performed and which asset, location or route it refers to. To create a new Work Order, select the option "Work | Work Orders"; The list of work orders will be displayed; ...