How do I change the preventive event date on the event form?
On the preventive
maintenance event form, you can postpone or delay the event date according to
the following rules:
- The new event date
must not be earlier than the previous event or later than the next one,
in order to maintain the order of the preventive maintenance;
- When preventive
maintenance is rescheduled (automatically or manually), fixed-date
events keep the same fixed/scheduled date;
- If the preventive automatically
creates a WO, it will be created on the new event date;
- If the event
already has a WO, the date cannot be changed;
- If after changing
the event date you want to restore the original date, simply delete
the Fixed Date value. On the next recalculation, the Estimated Date
will take on the date given by the recalculation.
To change the
preventive event date on the event form, follow these steps:
- Go to Work |
Preventive Maintenance | Maintenance Events;
- Select the
preventive event;
- Change the Fixed
Date field;
- Click on Save.
Related Articles
How to create a preventive maintenance?
Preventive maintenance specifies a set of maintenance actions to be performed based on a fixed recurrence or on meter values. To create a new preventive maintenance, select the option Work | Preventive Maintenances: The list of preventive ...
How to join plans on the preventive maintenance?
When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...
How to set the preventive maintenance plan replacement?
On the maintenance plans of a preventive maintenance, it is possible to select the replacement criteria. The replacement criteria can be the following: None main (Multiplier) Replacement The plan replacement rules are the following: All maintenance ...
How to define a maintenance plan tolerance in a preventive maintenance?
When creating a preventive maintenance, on the tab "Planned Work", you can add a Maintenance Plan and in that plan, you can add the following tolerances: AdvanceTolerance DelayTolerance The tolerance considers the following logic: AdvanceTolerance: ...
How to plan the preventive maintenance for several years?
The events are not all generated when the preventive maintenance is approved. The events are rescheduled daily according to a set of rules. The following rules: Events based on the recurrence: If the preventive has a daily plan, a maximum of 2 years ...