How to set a preventive maintenance with the work order closing date?
On the
work orders tab, it is possible to define the scheduling criteria that affected
the date of the following event, based on the previous work order.
The
closing date criterion is based on the work order SLA end date. This date can
be viewed on the work order file, on the planning. This date
is filled in when the work order state is configured with the SLA end option
active.
Example of
scenarios:
- Tolerance of zero days: Preventive
on the first Monday of every month
Event
| Expected Data
|
1
| 09/02/2022
|
2
| 09/03/2022
|
3 | ... |
- Tolerance of 10 days - Monthly
preventive every 9th day of the month
Advance
and delay tolerance of 10 days
Example of
an event inside the tolerance - The Event is opened on 02/09/2022, and
transitioned to an SLA end state on the 02/18/2022 (transition of SLA end
inside the 10 days tolerance)
Evento
| Expected Date
|
1
| 09/02/2022
|
2
| 09/03/2022
|
3
| 09/04/2022 |
- Example of
an event outside the tolerance -The Event is opened on 02/09/2022, and
transitioned to a SLA end state on the 02/20/2022 (transition of SLA end
outside the 10 days tolerance)
Event
| Expeted Data
|
1
| 09/02/2022
|
2
| 20/03/2022
|
3
| 20/04/2022
|
Tolerance of 365 days - The
tolerance of 365 days is equal to 0, that is, when applying the tolerance, it
returns to the same day as the event
Related Articles
How to create a preventive maintenance?
Preventive maintenance specifies a set of maintenance actions to be performed based on a fixed recurrence or on meter values. To create a new preventive maintenance, select the option Work | Preventive Maintenances: The list of preventive ...
Calculating Preventive Maintenance events with counters and Opening or Closure scheduling criteria
The cumulative reading value of a preventive maintenance event becomes the same as the last counter reading when: the Work Order has an associated preventive event; the event is the last one with an associated Work Order (most recent); the preventive ...
How to set a preventive maintenance with fixed date?
On the Work Orders tab, you can set the scheduling criteria to set the event on a fixed date, when applying this configuration, the events will always be created on the set date. This criterion is not influenced by the previous work order dates, that ...
How to set a preventive maintenance with the work order closing/opening date?
When creating a preventive maintenance, on the "Work Orders" tab, it is possible to define the scheduling criteria that affected the date of the following event, based on the previous work order. On the "Scheduling", it is possible to select one of ...
How to join plans on the preventive maintenance?
When creating a preventive maintenance, it is possible to replace maintenance plans when they occur on the same date or it is possible to join the several maintenance plans in a single work order. When the option “Join Plans” of a preventive ...